New warehouse dry store of ice cream factory side 35.7 x 183.5 m. included:
1)Packing material for production
2)Raw material for production
3)Chilled store
4)Ultra-clean interface 2
5)Ultra-clean interface 3
6)Ultra-clean workshop
7)Dry waste
8)Renovation area (dry store existing)
9)Substation
10)Tank farm
Project detailed design management and construction supervision the works as following:
•Preliminary design
•Detail engineering design for construction ventilation system sanitary system mechanical works electrical works included power supply lighting system fire protect fire fighting system and all building interior/exterior finishing & interior partition.
•Cost estimation, tender document and contract preparation
•Consulting for bidding to select contractor
•Construction supervision
•Project management
Name of Project | New Dry Store of Ice Cream Factory |
Location | Ladkrabang Industrial Estate, Bangkok |
Client | Unilever Thai Holding Ltd. |
Duration | February 2007 - January 2008 |
Project Cost |