Construction Supervision Consultant Services for Passenger Terminal Complex for Second Bangkok International Airport Project (Suvarnabhumi Airport)

Narrative Description

The passenger terminal building is a large single building having useful floor space of 563,000 square meter consists of 7-floor passenger lounge include 2 basements with useful floor space area of 182,000 square meter and 4-storey concourse building including basement with useful floor space area of 381,000 square meter.

Services Description

Construction supervision work consists of the following : 
• To provide all of the professional staff, services, supplies and equipment necessary to perform the CSC services to ensure that the works conform   to the construction contract.
• To co-ordinate the contractor’s operations with those of all other contractors and CSC with particular emphasis on interfaces between the contract and any other interfacing contracts schedule and cost control.
• To submit all correspondence to NBIA, with a copy to the project management consultant (PMC).
• To provide a detailed proposed construction schedule in computerized form prepared in the primavera project planner (P3 for windows).
• To prepare and maintain a cost control database in microsoft access compatible (MDB) files in bill of quantities Format.
• To provide detailed construction cost control information.
• To utilize a computerized system for controlling all documentation transmittals and submittals, using the expedition contract software by primavera system, Inc.
• To submit all documents as mentioned in TOR and as required by NBIA.
• To prepare a quality assurance plan for the services to be used during the implementation of each of the stages of the services.

 

Name of Project Construction Supervision Consultant Services for Passenger Terminal Complex for Second Bangkok International Airport Project (Suvarnabhumi Airport)
Location Samut Prakan Province
Client Airport of Thailand Public Company
Duration February 2003 - September 2007
Project Cost