Construction of 115/22 kV Substation and associated works consist :
•Power transformer of 115/22 kV, 20/25 MVA
•Circuit Breaker 123 kV, 1300A, 31.5 kA
•Disconnecting Switch 123 kV, 1300A, 31.5 kA
•24 kV Switchgear
•Surge Arrester 96 kV. 10 kA
•Grounding System
•123 kV. Transmission Line
•22 kV. Distribution Line
•22 kV. Distribution Transformers
Construction supervision of the following works:
•Construction of substation control building
•Construction of substation equipment foundations
•Construction of manhole, duct bank, underground cable and overhead distribution connecting to existing university's distribution system
•Construction of steel structure for 115 kV take-off and overhead ground structure
•Testing and commissioning of substation equipments
•Training University's staff for operating substation.
Name of Project | Construction Supervision of 115/22 kV Substation for Mahasarakham University |
Location | Mahasarakham Province |
Client | RTG/Mahasarakham University |
Duration | November 2001 - October 2002 |