The Construction of Wastewater Treatment System (SBR 3 and SBR 4) consists of stabilization pond size 20x40x6 m with production capacity of 2,800 cu.m./day.
The scope of works for Construction Supervision services consist of:
• Review design drawing and construction list
•Check, consider and control the construction schedule and methods.
•Recommend inspection of works according to construction contract.
•Control the shop drawing according with the works process.
•Check and consider for approver.
•Consideration, check and correct the obstacle in construction works.
•Coordinate with the relevant government agencies.
• Check and consider payments according to the contract.
•Preparation of weekly report, monthly report of the contractor works.
Name of Project | Construction Supervision of Wastewater Treatment System (SBR 3 and SBR 4) for Wellgrow Industrial Estate |
Location | : Chachoengsao Province |
Client | Wellgrow Industries Co., Ltd. |
Duration | May – Aug 2002 |
Project Cost |
© 2020 Seatec Group. All Rights Reserved.