1)Design 2 lane main road within the Phuket Airport with each lane being 3.5 m wide together with the 65 m long entrance junction into the parking platform at the ground floor of Passenger Terminal and Departure Platform on the second floor having the length of 110 m. including outside parking.
2)Airport infrastructure system design of
-115/33 KV electrical Substation and 33 KV electrical distribution system together with cable and assemblies for 3-storey building.
-Expansion of production and distribution water supply system that can produce 2,900 cu.m./day and reuse water system.
-Wastewater treatment system for 2,400 cu.m./day, sewage collection system and temporary waste storage building having a total area of 24 sq.m.
Consultancy Services for the Design consisting of:
•Conceptual Design and Preliminary Design.
•Detailed Design for construction, traffic management system, Various facilities together with calculation
•Prepare Cost Estimate
•Preparation of Specification
•Preparation of construction plans (Construction Stage and Construction Schedule).
•Bill of Quantities
•Preparation of Tender Documents and contract documents
Name of Project | Consultancy Services for Detailed Design of Road and Infrastructure for Phuket Airport (Fiscal Year 2009-2013) |
Location | Phuket Province |
Client | Airport of Thailand (Public) Co. Ltd. |
Duration | February 2011 - August 2011 (DD) : October 2012 - December 2018 (CM) |
Project Cost |
© 2020 Seatec Group. All Rights Reserved.