Environmental Quality Monitoring during Construction of Chiangmai International Airport (Fiscal Year 2006)

Narrative Description

The Airport of Thailand Plc (AOT) proposed the EIA report of Chiang Mai Airport Development regarding on runway expansion in the north side for 300 m (total 3,400 m) to the National Environmental Board and the EIA study was already approved.  According to the EIA report, AOT have to follow the Environmental Protection Measures to mitigate the environmenatl impacts both in construction and operation period. Thus, a company named "South East Asia Technology or SEATEC" was hired to monitor the Environmental Quality in fiscal year 2006 which is the year of construction period. The puopose of the study as follows:
1)To inspect and monitor the EPMs implementation during the construction period
2)To inspect and monitor the environmental quality regarding surface water quality, discharge water quality from  wastewater treatment system, air quality, noise level, vibration and socio-economic
3)To survey the noise impact from the airport in the areas NEF 30-40 and NEF 40
4)To control the environment in the airport and surrounding areas

Services Description

Project Environmental Quality Monitoring during Construction 
the works as follow :
•Review the  EPMs recommended in the EIA study of Chiang Mai Airport.
•Examine the existing project details/the result of EPMs implementation/survey of the impact areas from plane noise andattitude survey of surrounding communites.
•Analyse and assess the monitoring results/environmental quality monitoring and also propose additional monitoring measures and appropriate monitoring guildelines which is practical.
•Provide map of buildings in the impacted areas effected by noise, attitude survey of the owner of those buildings and order the severe areas regarding the attitude of the building's onwer.
Name of Project Environmental Quality Monitoring during Construction of Chiangmai International Airport (Fiscal Year 2006)
Location Chiangmai Province
Client Airports of Thailand Public Company Limited (AOT)
Duration December 2005 – September 2006
Project Cost