Construction of a new supply base to support the operation of petroleum exploration and production in the Gulf of Thailand. The area is located at Tambon Klai, Thasala District, Nakhon Si Thammarat Province. Project components in the sea are the construction of the jetty and breakwater. On-land project components are the materials storage building, office building, etc.
Environmental, Social and Health Impact Assessment (ESHIA) and Environmental Impact Assessment (EIA) for the construction of the project include the following:
• Collection of relevant data and reconnaissance survey of the project site.
• Study of the existing condition of environmental resources/value in the study area covering physical resources, biological resources, Human Used Value and Quality of Life
• Assessment of the impact from project development to environmental resources/value and risk assessment during construction and operation phases.
• Recommendation of mitigation measures to reduce the adverse effects and environmental monitoring program.
Name of Project | Environmental, Social and Health Impact Assessment (ESHIA)and Environmental Impact Assessment (EIA) Preparation for Chevron Thailand Shore Base Project |
Location | Nakhon Si Thammarat Province |
Client | Chuchawal-De Weger International Ltd./ Chevron Thailand Exploration and Production Ltd. |
Duration | November 2007 - April 2009 |