Building Work
-Feed End Building
-Fried End (Burnt Lime) Building
-ESP Building
-Service Walkway
Machine foundation and Tanks
-Line Kiln Foundation
-Machine foundation and Tanks
Road work and drainage system
Land Scarping
System work for the building
The services included the following works:
(1)Piling work
(2)Building structure and machine foundation
(3)Road work and drainage system
Name of Project | Detailed Design and Construction Supervision of Machine Foundation for Lime Kiln and Gasifier Plant Project |
Location | Kanchana Buri Province |
Client | Siam Cellulose Co., Ltd. |
Duration | September 2010 – March 2012 |
Project Cost |
© 2020 Seatec Group. All Rights Reserved.
Designed by A Must