Construction Supervision of Road, Drainage System and Slope Protection at Phramahajadee Santi Keeree Doi Mae Salong

Narrative Description

       SEATEC Group, Dynamic Engineering Consultants Co., Ltd. (DEC) carried out the construciton supervision for the drainage system of surface water and ground water along the roadside including protection for the land falling at the East of Srinakarintra-Stitmahasantikhiri Pagoda at Doi Mae Salong, Mae Pha Luang District, Chiang Rai Province, Slope protection is covered the approximated area 23,420 m2.
•Road 1234 from Sta. 3+100 to 3+833.230, total 733 m.
-Concrete road thick 23 cm, length 247 m.
-Asphaltic road thick 5 cm, length 486 m.
•Ground water and surface water drainage system along the road 
-Pipe culvert work length 55 m. 
-Side ditch length approx. 3,350 m. 
-Step drain length approx. 1,450 m.
-U-Ditch & Steel grating length 150 m.
•Side slope protection at the East of Pagoda for the area approximately 23,420 m2.
•Stair work

Services Description

Project construction supervision including :
•Supervision of all construction including engineering and architecture.
•Control and monitor the construction work plan.
•Reviewing and approving the as-built drawing and materials.
•Preparation and cash flow control as planned.
•Prepare monthly reports.
Name of Project Construction Supervision of Road, Drainage System and Slope Protection at Phramahajadee Santi Keeree Doi Mae Salong
Location Chiang Rai Province
Client Supreme Command Headquarters
Duration September 2001 – July 2003
Project Cost