Project detailed engineering design, tender management and construction supervision the works as follow :
Detailed Design
•Topographic survey of the route.
•Hydrologic surveys and studies.
•Geotechnical surveys and foundation designs.
•Bridge design, Road and civil designs, Design of electrical installations.
•Project management and coordination.
•EIA study.
•preparation of cost estimation.
•preparation of tender document and contract.
Construction Supervision
•Project management of all 4 routes.
•Construction supervision of route Bangkok : Taling Chan to Nakhon Pathom, length of 42 km. comprising track stuctures, railway stations, residential buildings, bridges, road crossing and signalling and communications.
Name of Project | Detailed Engineering Design, Tender Management and Construction Supervision of Track Doubling Project - Package 2 (total route length of about 174 km.) |
Location | Bangkok, Lop Buri Province, Chachoengsao Province, Nakhon Pathom Province |
Client | State Railway of Thailand |
Duration | DD August 1996 – July 1997 CM (Talingchan - Nakhon Pathom) July 2000 – January 2003 All Project August 1996 – April 2003 |
Project Cost |
© 2020 Seatec Group. All Rights Reserved.