Environmental Quality Monitoring during Operation of Chiangmai International Airport (Fiscal Year 2007

Narrative Description

       Airports of Thailand (Public) Co. Ltd. (AOT) let to prepare a report on the environmental impact assessment for Chiang Mai Airport Development Project (2004), for the impacts of the environment to expand the length of the runway to the north to have the runway length of 3,400 m with improvement expansion of the terminal building and improvement expansion of aircraft parking bay on the south side. Rapid Exit Taxiway construction and improvement of taxiway and parking bay, construction of aviation fuel pipeline system, and improved the car park and expansion of runways and taxiways on the north side within the Air Force Zone by a distance of about 300 meters (including the length of the runway 3,400 m). The report said that the National Environment Board has given approval to the AOT to implement the measures to reduce environmental impacts prevention and correction measures and environmental quality monitoring during both construction and operation periods in 2006. AOT was able to undertake the construction of the Chiang Mai Airport development Project Plan in 2007 in the process of partial construction and completed construction of some parts. Therefore, in fiscal year 2007, it is still monitoring the compliance of measures both in construction and operation. 

Services Description

     Consultancy services for monitoring of environmental quality both during construction and operation periods include:
•Review details of the project to propose the details of the implementation of current projects and demonstrate the various changes that have occurred and to assess the impact on implementation of the mitigation measures with accompanying photos graphs.
•Monitoring the implementation of measures to prevent and reduce the environmental impact monitoring on the actual performance of the Chuang Mai Airport compared with standard terminal that has been defined in the scope of works.
•Environmental quality monitoring during operation period include 6 plans such as monitoring the quality of surface water and quality of effluent from wastewater treatment systems, monitoring air quality, monitoring the noise, monitoring vibration, monitoring socioeconomic aspect and monitoring of public health.
Name of Project Environmental Quality Monitoring during Operation of Chiangmai International Airport (Fiscal Year 2007
Location Chiang Mai Province
Client Airport of Thailand (Public) Co. Ltd.
Duration January 2007 – November 2007
Project Cost