Port A3 international container terminal at Laem Chabang Part of Port Authority of Thailand project covers about 120,000 sq.m. The port consists of 30 x 350 m. wharf, 3 storey office building, 7-lane container truck check-point building, custom building, maintenance building, sub-electricity station building, fuel station, transformer and stand-by generator building, crane truck driver building, structural steel rack for container cooling system, 210 x 320 container yard, maintenance yard 26 x 26 m. and concrete road for vehicle in the project area.
Scopes of services are as followings:
•Supervise the construction of electrical system air conditioning system and sanitary system
•Inspect and monitor the work schedule
•Review and approve the construction drawing
•Review and approve the construction material
•Progress monthly report
Name of Project | Assistance for Design Review and Supervision of E&M Works for Area A3 Development Project at Laem Chabang Port |
Location | Chon Buri Province |
Client | Scott Wilson Kirkpatrick (Thailand) Ltd. |
Duration | March 2005 – May 2006 |
Project Cost |