1)Songkhla Deep-Seaport
Expansion of deep-water port for container cargo at another one Length 180 m. width 30 m. increase in length from 510 m. to 690 m., silo size 6720 sqm. The old port improvements to accommodate gantry crane capacity of 40 tons. 120 m. wide navigation channel improvement length 4 km 9 m. deep including boat basin to 300 m. in diameter. Expansion of breakwater 300 m. long and 56 rai of land reclamation for container yard and container freight station (CFS).
2)Phuket Deep-Seaport
Improve the existing port. The separation of passenger or tourist activities of cargo handling activities.Including the construction of one passenger berths 3.50 m.wide 40 m. Long, harbor patrol , wharf raft carrying latex, one passenger building area 1,620 m2 including road and utilities improvements within the project area.
Name of Project | Environmental Impact Assessment and Detailed Engineering Design for the Expansion of Songkhla and Phuket Deep-Seaports Project |
Location | Songkhla Province, Phuket Province |
Client | Marine Department |
Duration | September 1997 - February 1999 |
Project Cost |